Creating Task Dependencies

Creating Task Dependencies

Task dependencies help you define the order in which tasks need to be completed. With this feature, you can ensure that certain tasks don't begin until others are finished—perfect for keeping projects on track and avoiding bottlenecks.

What Are Predecessor and Successor Task Dependencies?

In ActiveCollab, a Predecessor should be completed before its Successor. Task dependencies allow you to create a link between tasks so that:
Successor depends on the Predecessor
→ Successor can only start after the Predecessor is completed.
This is especially useful for complex projects with multiple steps or teams involved. When setting up Due dates for your tasks with dependencies, make sure the Predecessor's deadline is before the due date of its Successor. Predecessor tasks should be completed before the current task. Member assigned to the current task will be notified when each Predecessor task is finished.
You will see a warning sign when Due dates overlap.

How to Add a Task Dependency?

There are two ways to set up task dependencies:
You can set up task dependencies directly from the task interface:
  • Step 1: Open the task to which you wish to add a dependency.
  • Step 2: Scroll down to the "Dependencies" section.
  • Step 3: Click “Add Dependency”.
  • Step 4: Search for and select the task(s) this task depends on.
  • Step 5: Select the Predecessor or Successor dependency.
  • Step 6: Once selected, the task will be linked as a dependency.
  • Video Tutorial: https://vimeo.com/1040200056
You can set up task dependencies from the timeline view:

  • Step 1: Open your project in ActiveCollab.
  • Step 2: In the top right corner of the task list, click on the "Timeline" tab to switch to the Gantt view.
  • Step 3: Locate the two tasks you want to link:
    • The Predecessor (the one that needs to be completed first).
    • The Successor (the one that depends on the parent).
  • Step 4: Hover over the Predecessor task bar in the timeline.
    • You’ll see small circles appear on the left and right edges of the bar—these are the linking points.
  • Step 5: Click and hold one of the circles, then drag your cursor toward the Successor task.
  • Step 6: Drop the line onto the corresponding circle on the Successor task bar to create a dependency.
  • Step 7: Once connected, you’ll see an arrow between the tasks indicating a dependency.
  • Tips:
    • You can add multiple dependencies to a single task.
    • Adjusting one task will automatically adjust dependent tasks, keeping your schedule aligned. Changing the date of one task opens a window showing how that task affects others (Smart Rescheduling)
    • You’ll see visual indicators (such as a chain icon) to represent dependency relationships.
  • Video Tutorial: https://vimeo.com/1040200072

How can I remove a Dependency?

You can remove a Task dependency in two ways as well:
To remove a dependency from the task modal:
  • Step 1: Open the task.
  • Step 2: Go to the Dependencies section.
  • Step 3: Click the “X” next to a task to remove the dependency.
  • Video Tutorial: https://vimeo.com/1040200122
To remove a dependency from the timeline view:

  • Step 1: Open the Timeline view within the Project.
  • Step 2: Click on the arrow line of the dependency you wish to remove.
  • Step 3: Select Remove dependency
  • Video Tutorial: https://vimeo.com/1040200102

Can’t find your answer?

Start Your Free Trial

Enter your email to get 14 days of ActiveCollab absolutely free, without any limitations.


or

By signing up you agree to ActiveCollab's Terms of Service & Privacy Policy.

Great! Just a few seconds, and you're in.

All done! Redirecting you to your account.

Continue

You're only one confirmation away from your new workspace.
Check your email, and see you soon!

We detected you already have an ActiveCollab account.

You can log in to an excisting account or you may start a new one

Sorry, we couldn't create an account for you at this moment.
Please double check your email address. If the issue still persists, please let us know by sending an email to support@activecollab.com


Try Again